Installation Gallery · Controls and automation
Uzbekistan substation upgrades and SCADA integration
Where an Uzbekistan grid upgrade keeps part of the existing station control system, issue the integrator’s signal list with the transformer RFQ. Confirm tap position, cooling feedback, alarms and trips, along with the required interfaces and terminal identification.
- Obtain an agreed I/O list and terminal plan before wiring is frozen. Identify who supplies any interface equipment and who adapts the station system.
- Split factory signal checks from end-to-end site checks. Include who witnesses each step, who closes issues and which records are required before control handover.
Planning a similar transformer installation?
Share your existing station control interface and the signals needed for cooling, taps, alarms and trips. Email the I/O list if it is ready for review.