Transformer Selection Guide

Transformer Selection Guide: How to Choose the Right Transformer

Buying guide · Tianhua Transformer engineering team

Quick answer

Fix seven things in order: load in kVA, voltage ratio, transformer type (oil-immersed, dry-type, pad-mounted, pole-mounted or compact substation), standard (IEC or IEEE), cooling, losses and site conditions. Estimate peak simultaneous demand in kVA, allow for planned growth, then shortlist an available rating that meets the project conditions.

This guide from our design engineers walks through each decision with formulas, tables and the information we need to quote.

Get a quote in 24 hoursDownload catalogue

Oil-immersed power transformer installed on a concrete foundation in an outdoor substation
Outdoor oil-immersed power transformer with radiator banks, bushings and a concrete foundation.

At a glance

1. CapacityPeak demand in kVA, with an allowance based on the project’s load growth plan
2. VoltagePrimary = supply network; secondary = equipment voltage; add taps
3. TypeOil-immersed outdoors, dry-type indoors, pad-mounted for underground networks, pole-mounted for overhead lines
4. StandardIEC 60076 (mostly 50 Hz) or IEEE / ANSI C57.12 (mostly 60 Hz)
5. CoolingONAN for distribution; ONAF / OFAF for larger units
6. LossesCompare total cost of ownership, not price alone
7. SiteAltitude, ambient temperature, corrosion, space and fire rules

1. How do I size a transformer in kVA?

Start with the maximum load expected to run at the same time. Use measured peak demand or a load schedule that shows which loads operate together. If the peak load is in kW, use the power factor at that operating point to estimate kVA.

  • From peak real power: kVA = kW ÷ power factor
  • Balanced three-phase from current: kVA = √3 × line-to-line voltage (V) × line current (A) ÷ 1,000
  • Single-phase: kVA = voltage (V) × current (A) ÷ 1,000

Worked example: A peak of 640 kW at a power factor of 0.80 is 800 kVA. If the project allows 20% for growth, the target is 800 × 1.20 = 960 kVA. A 1,000 kVA unit is a candidate if it can carry the required load under the specified conditions.

Choose the allowance from the expansion plan. Before finalising the rating, confirm any motor-starting, harmonic or standby duty requirements and check the available capacity at the site’s temperature and altitude. These are examples of commonly offered ratings:

StandardCommon three-phase ratings (kVA)
IEC100, 160, 200, 250, 315, 400, 500, 630, 800, 1,000, 1,250, 1,600, 2,000, 2,500
IEEE / ANSI45, 75, 112.5, 150, 225, 300, 500, 750, 1,000, 1,500, 2,000, 2,500, 3,750, 5,000

The table gives reference full-load currents at nominal secondary voltage for balanced three-phase units. Confirm cable and switchgear sizing against the project’s installation and protection requirements.

LV voltageFull-load current
400 V250 kVA ≈ 361 A, 630 kVA ≈ 909 A, 1000 kVA ≈ 1,443 A, 1600 kVA ≈ 2,309 A, 2500 kVA ≈ 3,608 A
480 V250 kVA ≈ 301 A, 630 kVA ≈ 758 A, 1000 kVA ≈ 1,203 A, 1600 kVA ≈ 1,925 A, 2500 kVA ≈ 3,007 A
208 V250 kVA ≈ 694 A, 630 kVA ≈ 1,749 A, 1000 kVA ≈ 2,776 A

2. Which voltage ratio and taps?

The primary voltage is your supply network, for example 6.6, 10, 11, 13.8, 20, 33 or 34.5 kV. The secondary is the voltage your equipment uses: 400 V or 415 V in IEC regions, 208Y/120 V or 480Y/277 V in North America, or 690 V and above for industry and inverters.

Add a tap changer so the output can be adjusted: an off-circuit tap changer (typically ±2 × 2.5%) where the grid voltage is stable, or an on-load tap changer (OLTC) where it varies under load. Also give the vector group, for example Dyn11 for distribution transformers.

3. Which type of transformer?

TypeTypical rangeBest forGuide
Oil-immersed distribution30–3,150 kVA, 6–35 kVOutdoor substations, utilities, industry; lowest cost per kVA, good overload capacityRead
Dry-type (cast resin / VPI)30–2,500 kVA, 6–24 kVIndoors and fire-sensitive sites: buildings, hospitals, data centers, metroRead
Pad-mounted45–5,000 kVA three-phaseUnderground cable networks, housing, commercial, solar; locked cabinet on a concrete padRead
Pole-mounted5–167 kVA single-phaseOverhead rural and residential linesProducts
Compact substation6–40.5 kVMV switchgear, transformer and LV board in one enclosure; fast installationRead
Power transformer35–220 kV, 0.8–360 MVAGrid substations, power plants, heavy industryRead

4. IEC or IEEE?

IEC 60076IEEE / ANSI C57.12
Where usedEurope, Middle East, Africa, most of AsiaNorth America and many Latin American and Philippine utilities
FrequencyMostly 50 HzMostly 60 Hz
Typical LV400 V, 415 V, 433 V208Y/120 V, 240 V, 480Y/277 V, 600 V
RatingskVA steps 100, 160, 250, 400, 630…kVA steps 45, 75, 112.5, 150, 225, 300, 500…

The standard changes ratings, insulation levels, test values, bushing layout and nameplate, so state it in the enquiry. Tianhua designs to both, as well as China GB 1094.

5. Cooling: ONAN, ONAF, OFAF or AN / AF

CodeMeaningUsed for
ONANOil natural, air naturalStandard for distribution transformers
ONAFOil natural, air forced (fans)Extra capacity at peak load on larger units
OFAF / ODAFOil pumped through coolers with fansLarge power transformers
AN / AFDry-type, natural air or fansDry-type transformers; fans give short-term extra capacity

6. Losses, efficiency and total cost

No-load (core) loss is paid 24 hours a day, whatever the load. Load (copper) loss rises with the square of the load. A cheaper transformer with higher losses often costs more over its life.

Compare offers by total cost of ownership = price + A × no-load loss + B × load loss, where A and B are the capitalised values of 1 kW of loss over the transformer life.

For lightly loaded networks, amorphous alloy (SH15, SCBH15) or S20 / S22 low-loss designs usually give the lowest total cost. Check the efficiency rule in your country, such as EU Ecodesign Tier 2, US DOE 2016 or China GB 20052.

See energy-efficient and amorphous transformers

7. Site conditions to check

  • Altitude above 1,000 m: air cools less and insulates less, so the design must be adjusted
  • Ambient temperature above 40 °C (desert, Middle East): derate or design for higher ambient
  • Coastal or industrial air: specify a corrosion class such as C4 or C5 and the paint system
  • Indoor fire rules: dry-type or natural ester (FR3) fluid
  • Space and access: maximum dimensions, weight, door and crane limits
  • Noise limits near homes, hospitals and offices

8. What to send for a quotation

  • rated power (kVA or MVA) and quantity
  • primary and secondary voltage, frequency (50 or 60 Hz) and vector group
  • standard: IEC 60076, IEEE / ANSI C57.12, GB or a utility specification
  • tap changer range and type
  • loss requirement or efficiency rule (or loss capitalisation values for TCO evaluation)
  • site conditions: indoor or outdoor, altitude, ambient temperature, corrosion class
  • destination port or site and preferred Incoterm

A single-line diagram or load list is enough to start. Our engineers check the sizing for free.

9. Common mistakes to avoid

  • Choosing a rating before checking peak demand, planned expansion and site conditions
  • Comparing offers on price without comparing losses
  • Forgetting the standard and frequency, which changes the whole design
  • Using an oil-immersed transformer indoors where fire rules require dry-type
  • Leaving out altitude, temperature or corrosion conditions

Who makes these transformers

Interior of Tianhua’s 220 kV Transformer Test Center
Factory Testing
Inside Tianhua’s 220 kV Transformer Test Center

This guide is written by the engineering team of Jiangsu Tianhua Transformer Co., Ltd., a transformer manufacturer founded in 2013 in Xuzhou, Jiangsu, China. Every unit is designed, built and tested in our own 107,000 m² plant: core cutting, winding, drying, resin casting, tanks, radiators, assembly and testing. You deal directly with the factory engineers.

  • 500+ employees, including 7 senior engineers
  • ISO 9001 quality system; IEC, IEEE / ANSI and GB designs
  • SSZ11-40000/110 passed short-circuit and full type tests at a national test center
  • Exported to more than 30 countries and regions

About Tianhua · Factory and testing · Certificates · Projects

Frequently asked questions

How do I calculate transformer size?

Estimate the maximum simultaneous demand in kVA. If you know peak kW and the power factor at that load, divide kW by power factor. Add the capacity needed for planned expansion and verify that an available rating meets the site and operating requirements.

What size transformer do I need for 500 kW?

At a power factor of 0.80, a 500 kW peak is 625 kVA. A 20% growth allowance gives 750 kVA. A 25% allowance gives 781.25 kVA. At 25%, consider 800 kVA if offered, or 1,000 kVA if the approved range jumps from 750 to 1,000 kVA. Confirm the applicable ratings and site duty before ordering.

Should I choose an oil-immersed or dry-type transformer?

Oil-immersed costs less per kVA and suits outdoor sites. Dry-type has no oil, so it suits indoor and fire-sensitive sites such as hospitals, high-rise buildings and data centers.

What is the difference between IEC and IEEE transformers?

IEC 60076 is used in most 50 Hz markets; IEEE / ANSI C57.12 in North America and other 60 Hz markets. They differ in ratings, test levels, voltages, bushing layout and nameplate.

Can Tianhua help me choose the right transformer?

Yes. Send your load list or single-line diagram to sale@thatransformer.com and our engineers recommend the rating and type, with a datasheet and price within 24 hours.

What is the most common distribution transformer size?

For commercial and light industrial sites, 315 to 1,600 kVA at 400 V is most common. Utilities often use 100 to 630 kVA units on their distribution networks.

Not sure which transformer you need?

Send capacity, voltages, standard, quantity and destination. Our engineers reply with a datasheet and price within 24 hours.