Two transformers sharing one approach road need two credible delivery slots. For German grid reinforcement tenders, ask for a bay-by-bay plan that ties factory release, route and heavy-haul coordination, crane access and the owner’s outage window to each unit. Check whether the first crane setup or laydown area blocks the second transport.
Request a separate site-ready date, delivery sequence and fallback plan for each bay. Where the site relies on a timed road movement, name the party responsible for coordinating the carrier, time slot and access restrictions.
Planning a similar transformer installation?
Send both transformer ratings and each bay’s required delivery date. Flag any shared access, crane or outage limits that affect the delivery sequence.