Paraguay transformer unloading, placement and handover
Ask bidders to name both the delivery point and the point where they hand over the transformer. For an ANDE or utility EPC tender, have them price inland haulage, crane and rigging for unloading, and final placement on the foundation as separate items. State who takes custody at each handover and who arranges customs coordination if it is in scope.
Use the same handover point in the carrier and installer scopes. If the contract calls for factory witnesses, site testing or Spanish-language acceptance documents, identify who provides them and who signs the final on-site acceptance.