110 kV Transformer Supply in South America

Back to project overview

Project case study

Local Oil Sourcing for a 110 kV Transformer Project

Tianhua supplied 110 kV power transformers and coordinated the local sourcing of insulating oil. With customer approval, an Argentine supplier delivered the oil directly to the project site. Tianhua estimates that this pilot reduced the total transformer cost by about 6%.

Power transformer with radiator banks and bushings at an outdoor substation
Power transformer at an outdoor substation

Project scope and delivery

Equipment
110 kV power transformers
Tianhua’s scope
Transformer supply and coordination of local insulating oil procurement
Oil delivery
Direct to the project site from the approved supplier

What EPC Buyers Should Compare

Tianhua’s project summary attributes the pilot savings to sourcing the oil locally and shipping it straight to site. This avoided the import duty and ocean freight associated with routing the oil through China.

Compare total cost at the same delivery point

Ask each bidder to separate the transformer, insulating oil, freight and any on-site oil treatment and filling in the quote. Include the local oil price and delivery to site when comparing both sourcing options.

Agree on oil acceptance and warranty before award

Specify the approved oil and batch acceptance records. Name who approves the local supplier and who procures, receives, treats and fills the oil. If the buyer or a third party supplies it, ask each bidder to state in writing how that affects the transformer warranty and which approvals and records are required.

Align oil delivery with the installation schedule

Coordinate the transformer arrival, local oil delivery and the site team’s availability for oil treatment and filling. Ask bidders to show these dates and dependencies in their proposed schedule.

Request pricing for a similar 110 kV project

Share the MVA rating, voltage ratio, quantity, delivery location and required date. Tell us whether insulating oil and on-site oil services should be included in the quote.