Installation Gallery · Site assembly
UAE transformer site assembly, oil filling and warranty
In the UAE tender, name who releases the transformer for radiator assembly and oil filling, who accepts the oil and assembly records, and who signs mechanical completion. For a phased development, assign each approval a date ahead of the relevant energization milestone.
If the EPC appoints a third-party installer, agree in writing which work the supplier must witness, which records the installer must submit and how third-party work affects the warranty. Quote vendor site support and any return visits separately so the field team and commercial team plan against the same scope.
Planning a similar transformer installation?
Share the first energization date and the planned installer. Specify who will handle radiator assembly and oil filling, and what vendor support you want quoted.